Added-crew versus window remedy ================================ One relief mowing crew and machine were added for all five years and compared with extending the fall window. Calendar-aware execution is used throughout. Added-resource cost uses: - 1,200 CAD per crew-day; - 900 CAD per machine-day; - 8% supervision; - 10% overhead; - 2,500 CAD seasonal overhead per relief crew-year. Results ------- 20 episodes, seed 7, 59 segments. .. list-table:: :header-rows: 1 * - Case - Window - Extra crews - Completed P50 - Mean risk - Action cost P50 - Added resource P50 - Total cost P50 * - Baseline - 75 - 0 - 87.6% - 0.0502 - 264,047 - 0 - 264,047 * - Extra crew - 75 - 1 - 98.0% - 0.0332 - 293,706 - 529,411 - 823,084 * - Window - 90 - 0 - 95.9% - 0.0365 - 285,490 - 0 - 285,490 * - Window - 105 - 0 - 98.1% - 0.0333 - 294,012 - 0 - 294,012 The added crew recovers almost all calendar-aware scope, but its total cost is about **823,000 CAD** versus **294,000 CAD** for the 105-day window. Under these assumptions, extending the window is substantially cheaper than adding a crew and machine. Seasonal overhead for the window itself is not modelled. 590-segment scale test ---------------------- A replicated 590-segment instance uses 30 base crews, 10 relief mowing crews, and 10 relief machines. The fixed plan is exact; annual re-solves use Fresh Solutions. .. list-table:: :header-rows: 1 * - Case - Window - Extra crews - Completed P50 - Mean risk - Action cost P50 - Added resource P50 - Total cost P50 * - Baseline - 75 - 0 - 84.5% - 0.0667 - 2,536,614 - 0 - 2,536,614 * - Extra crew - 75 - 10 - 98.3% - 0.0325 - 2,931,649 - 5,357,421 - 8,278,357 * - Window - 90 - 0 - 95.9% - 0.0368 - 2,844,469 - 0 - 2,844,469 * - Window - 105 - 0 - 98.1% - 0.0328 - 2,931,649 - 0 - 2,931,649 Runtime: fixed exact 49.7 s; remedy sweep 344.4 s for 20 episodes. The extra-crew action cost already equals the 105-day window total, so **any positive resource rate** makes the crew option more expensive. At 59 segments, the break-even resource rate is only 0.058% of the assumed day rates. The window remedy dominates under these assumptions. Limits ------ - 59 segments only; not a 590-segment cost comparison. - Extra crew and machine are available for all five years. - Added resource cost uses prototype day rates and overhead fractions. - Window extension carries no added seasonal overhead or supervision in this comparison. - No safety, access, asset-owner priority, or field-calibration claim.