Chance-constrained capacity =========================== This extends the sampled budget chance constraint to capacity: at most two of 20 training paths may exceed budget and at most two may exceed capacity in each year. Both constraints are sampled; this is not a distributional guarantee. Results ------- .. list-table:: :header-rows: 1 * - Plan - 5-year cost P10-P90 - Mean risk - Budget violation - Capacity violation * - Chance capacity - 199,709-248,168 - 0.0516 - 22.0% - 0.0% * - Chance budget only - 198,743-247,028 - 0.0516 - 21.0% - 0.0% * - Nominal balanced - 269,679-333,777 - 0.0294 - 93.0% - 0.0% Chance capacity nominal cost: **222,076 CAD**; 170 actions. Chance capacity does not improve the out-of-sample result. Budget violation is 22% versus 21% for budget-only chance, risk is unchanged, and out-of-sample capacity violation is already 0% in the test set. The budget-only plan is better in this test. Interpretation -------------- The sampled capacity relaxation does not help because the test paths do not show capacity violations and the budget constraint remains tighter. The experiment is a negative result for this parameter set. A better next step would be an operational recourse model or a distributional chance constraint with more training paths. Limits ------ - Sampled constraints, not distributional. - 20 training paths; 100 test paths. - Shared static decisions; no recourse. - No risk, weather, outage, safety, asset-owner priority, or field calibration.