Weather/outage remedies ======================= The remedy comparison tests whether additional crew/machine capacity, a smaller first-year scope, or a longer window improves the assumed weather/outage calendar result. It uses the same 20 rolling episodes and 50 calendars per episode as the all-episode stress scan. Added capacity is costed at 1,200 CAD per crew-day and 900 CAD per machine-day against the 60,000 CAD first-year budget. These are prototype rates, not contractor quotes. Results ------- .. list-table:: :header-rows: 1 * - Remedy - Scenario full completion - Added cost P50 - Total cost P50 - Budget feasible * - Baseline - 13.2% - 0 - 59,875 - 100% * - +1 shared crew - 13.2% - 10,800 - 70,761 - 0% * - +1 shared crew + machine - 92.9% - 80,850 - 140,800 - 0% * - +1 shared machine - 13.2% - 8,100 - 68,061 - 0% * - 10% scope reduction - 23.4% - 0 - 53,888 - 100% * - 20% scope reduction - 44.9% - 0 - 47,900 - 100% * - 10% scope + 90-day - 54.9% - 0 - 53,888 - 100% * - 20% scope + 90-day - 66.4% - 0 - 47,900 - 100% * - 90-day window - 41.5% - 0 - 59,875 - 100% * - 105-day window - 61.9% - 0 - 59,875 - 100% * - **20% scope + 105-day** - **93.9%** - 0 - **47,900** - **100%** The **20% scope + 105-day** case is the best budget-feasible completion case. It is a proportional scope reduction, so the risk effect of deferring 20% of work is not evaluated here. A crew alone or machine alone does not improve completion because mowing and mechanical work require both. The crew-plus-machine case is the strongest full-scope completion remedy, but its median total first-year cost is about 140,800 CAD against the 60,000 CAD budget. Limits ------ - Capacity and scope remedies are hypothetical scheduling tests, not contractor commitments. - Crew-day and machine-day rates are prototype assumptions, not contractor quotes. - Scope reduction applies proportionally to work-item hours; it is not a risk-ranked deferral policy, and the deferred risk is not evaluated. - The calendar is assumed: independent weather loss and a fixed outage block. - Only first-year shift scheduling is tested; access, later years, and safety are not certified.