Weather/outage-aware recourse ============================= This comparison adds an assumed annual crew calendar to the rolling-recourse policy. Each year observes cost, hours, and capacity, and the execution calendar contains five fixed outage days plus independent 20% weather-loss probability per day in a 75-day fall window. Three cases are compared: - **calendar-naive**: keep the resource-feasible plan and accept partial execution; - **forecast-aware**: plan against an independent synthetic forecast calendar, then execute under the actual calendar; - **calendar-aware**: defer unscheduled actions until every retained action fits the observed calendar. The forecast is a synthetic draw from the same assumed distribution, not a forecast product. The observed-calendar case uses within-year calendar information before deferral. These are calendar policies, not stochastic dynamic programs. Results ------- 20 episodes, seed 7. .. list-table:: :header-rows: 1 * - Case - Budget violation - Completed scope P50 - Retained scope P50 - Mean risk - Cost P50 - Unscheduled h - Calendar deferrals * - Calendar-naive - 0.0% - 88.4% - 99.4% - 0.0480 - 297,595 - 605.9 - 0.0 * - Forecast-aware - 0.0% - 86.2% - 88.3% - 0.0526 - 264,470 - 64.7 - 39.2 * - Calendar-aware - 0.0% - 87.6% - 87.6% - 0.0502 - 264,047 - 0.0 - 39.9 Forecast awareness reduces unscheduled work from 605.9 h to 64.7 h, but forecast error remains. Observed-calendar awareness eliminates unscheduled retained work but costs about 1.4 percentage points of mean scope versus forecast awareness and raises mean risk. Neither aware case lowers risk; both convert partial work into deferred scope. 590-segment scale test ---------------------- A replicated 590-segment instance scales the workforce to 30 crews and 30 machines. The fixed plan is exact; annual re-solves use Fresh Solutions. .. list-table:: :header-rows: 1 * - Case - Budget violation - Completed scope P50 - Retained scope P50 - Mean risk - Cost P50 - Unscheduled h * - Calendar-naive - 0.0% - 85.9% - 99.6% - 0.0617 - 2,942,470 - 7,377 * - Forecast-aware - 0.0% - 83.6% - 86.4% - 0.0713 - 2,539,520 - 681.5 * - Calendar-aware - 0.0% - 84.5% - 84.5% - 0.0667 - 2,536,614 - 0.0 Runtime: fixed exact 48.6 s; 20 weather episodes 220.8 s. Forecast error leaves 681.5 h unscheduled at scale, while observed-calendar awareness eliminates unscheduled retained work. The instance is replicated, not a real network, and the heuristic makes no global-optimality claim. Limits ------ - Forecast awareness uses a synthetic calendar draw, not a weather forecast. - Observed-calendar awareness uses within-year information before deferral. - Weather loss is independent per day and assumed, not measured. - The outage block is assumed, not an asset-owner schedule. - Whole actions are deferred when they cannot be completed, so the aware cases are conservative. - No safety, asset-owner priority, access, or field-calibration claim.