Contractor capacity and cost
P7.2 builds a transparent contractor cost and capacity plan from explicit requests and profiles.
Profiles and requests
ContractorProfile records contractor id, offered methods, crews, machines, base rate per capacity
unit, travel rate, supervision fraction, overhead fraction, risk fraction, annual capacity, and
currency.
ResourceRequest records request id, contractor, method, year, capacity units, and travel distance.
Cost build-up
For each request the plan records separate lines:
base: capacity units times rate;travel: distance times travel rate;supervision: base times supervision fraction;overhead: base plus travel plus supervision times overhead fraction;risk: base times risk fraction.
resource_plan records cost by contractor and year. Every line names its request source.
Capacity
Annual capacity is checked by contractor and year. A missing profile, an unoffered method, or excess
capacity is a named RESOURCE-* violation. Missing evidence is never replaced by a zero rate.
from brushline.tactical.resources import build_resource_plan
plan = build_resource_plan(
plan_id="resources",
instance_id="corridor",
requests=requests,
profiles=profiles,
)
assert plan.feasible
Limits
Capacity is annual, not daily or seasonal.
The profile rates are supplied assumptions; no vendor quote is implied.
The plan does not assign crews to days; P7.4 owns the work order.