Weather and outage stress

The operational stress test applies an assumed weather and outage calendar to the median rolling policy’s first-year shift package. It is a feasibility screen, not a forecast, outage schedule, or safety certification.

Assumptions

  • 75-day fall work window.

  • Fixed 5-day outage block.

  • Independent 20% weather-loss probability on each day in the window.

  • 50 scenarios, seed 7.

  • The baseline uses the same 75-day window with no blocked days.

Network result

Baseline: feasible, 116 shift assignments, 813.7 productive hours, 8.5 travel hours, 63 days used.

Stress:

  • fully feasible in 0/50 scenarios;

  • mean work completion: 93.4%;

  • median unscheduled work: 50.2 hours;

  • P90 unscheduled work: 97.7 hours;

  • mean blocked days: 19.4;

  • median shift assignments: 107.

The assumed calendar removes enough field days that no sampled scenario schedules every work item. The package completes most hours but leaves a median 50 hours unscheduled. This is a capacity and calendar finding, not evidence that the policy is field-infeasible.

Interpretation

The first-year policy package was feasible with no weather or outage closures. Under the assumed calendar, it is not fully schedulable. The likely remedies are a longer window, additional crews or machines, a smaller first-year scope, or a policy that reserves weather slack. Those are design choices, not automatic conclusions.

Limits

  • Weather loss is an independent per-day assumption, not a forecast or field record.

  • The fixed outage block is assumed, not an asset-owner outage schedule.

  • Only the median policy episode and its first year are stressed.

  • No field calibration, safety certification, or clearance standard is claimed.

All-episode scan

The calendar stress was repeated for all 20 rolling episodes, with 50 scenarios per episode.

Metric

Value

Baseline 75-day feasible

50.0%

Scenario-level full completion

13.2%

Episodes with full stress completion

2 of 20

Mean work completion

85.6%

Unscheduled hours P50

127.5

Unscheduled hours P90

372.3

Failure sources across the 20 episodes:

  • fall-window capacity: 10 episodes;

  • weather/outage calendar: 8 episodes;

  • crew capacity: 0 episodes;

  • fully feasible: 2 episodes.

The 75-day window is the primary constraint. Increasing the window improved scenario-level full completion to 40.2% at 90 days and 62.8% at 105 days, with mean unscheduled work falling from 165.8 to 83.7 and 38.3 hours. A longer window alone does not reach full completion under the assumed weather calendar.