Weather and outage stress
The operational stress test applies an assumed weather and outage calendar to the median rolling policy’s first-year shift package. It is a feasibility screen, not a forecast, outage schedule, or safety certification.
Assumptions
75-day fall work window.
Fixed 5-day outage block.
Independent 20% weather-loss probability on each day in the window.
50 scenarios, seed 7.
The baseline uses the same 75-day window with no blocked days.
Network result
Baseline: feasible, 116 shift assignments, 813.7 productive hours, 8.5 travel hours, 63 days used.
Stress:
fully feasible in 0/50 scenarios;
mean work completion: 93.4%;
median unscheduled work: 50.2 hours;
P90 unscheduled work: 97.7 hours;
mean blocked days: 19.4;
median shift assignments: 107.
The assumed calendar removes enough field days that no sampled scenario schedules every work item. The package completes most hours but leaves a median 50 hours unscheduled. This is a capacity and calendar finding, not evidence that the policy is field-infeasible.
Interpretation
The first-year policy package was feasible with no weather or outage closures. Under the assumed calendar, it is not fully schedulable. The likely remedies are a longer window, additional crews or machines, a smaller first-year scope, or a policy that reserves weather slack. Those are design choices, not automatic conclusions.
Limits
Weather loss is an independent per-day assumption, not a forecast or field record.
The fixed outage block is assumed, not an asset-owner outage schedule.
Only the median policy episode and its first year are stressed.
No field calibration, safety certification, or clearance standard is claimed.
All-episode scan
The calendar stress was repeated for all 20 rolling episodes, with 50 scenarios per episode.
Metric |
Value |
|---|---|
Baseline 75-day feasible |
50.0% |
Scenario-level full completion |
13.2% |
Episodes with full stress completion |
2 of 20 |
Mean work completion |
85.6% |
Unscheduled hours P50 |
127.5 |
Unscheduled hours P90 |
372.3 |
Failure sources across the 20 episodes:
fall-window capacity: 10 episodes;
weather/outage calendar: 8 episodes;
crew capacity: 0 episodes;
fully feasible: 2 episodes.
The 75-day window is the primary constraint. Increasing the window improved scenario-level full completion to 40.2% at 90 days and 62.8% at 105 days, with mean unscheduled work falling from 165.8 to 83.7 and 38.3 hours. A longer window alone does not reach full completion under the assumed weather calendar.