Scenario-optimized planning
The scenario-optimization experiment asks whether re-planning after uncertainty is revealed would beat a fixed nominal plan. It samples cost, productive-hours, and capacity factors, evaluates the fixed balance plan under each scenario, and re-solves the exact stateful MILP in each scenario.
The comparison is a hindsight adaptive upper bound, not a deployable adaptive policy. The scenario-specific plan sees the sampled factors before choosing treatments. It measures the value of being able to re-plan; it does not model forecast updates, contractual switching, or a policy that can be executed without knowing the future.
Scenarios
Each scenario draws lognormal multipliers with mean one:
treatment cost, sigma 0.18;
productive hours, sigma 0.15, where higher hours means lower productivity;
contractor/crew capacity, sigma 0.15.
The network prototype uses 30 scenarios and seed 7. The fixed plan is the balanced 60,000 CAD/year MILP plan. The adaptive plan uses the same annual budget and method set, with costs and hours scaled and capacity scaled by the scenario factors.
Fixed-plan evaluation
The fixed plan’s actions are held constant. Cost and hours are scaled; its risk is unchanged because risk depends on the treatment schedule, not on the cost or hours draws. Annual budget and capacity violations are recorded separately.
The risk-equivalent objective adds a normalized feasibility penalty:
risk + cost_weight * cost / 100000 + hours_weight * hours / 100000
+ budget_overrun / total_budget + capacity_shortfall / total_capacity
The adaptive plan’s objective uses the same risk/cost/hours weights and is feasible by construction. Regret is the fixed objective minus the adaptive objective. The penalty is a declared scoring choice, not a monetary fine.
Result
For the 8,737 ha, 59-segment prototype:
the fixed plan exceeded its annual budget in 56.7% of scenarios;
the fixed five-year cost band was 249,742–371,650 CAD;
the adaptive five-year cost band was 298,055–299,452 CAD;
the fixed plan’s mean risk was 0.0294; the adaptive plan’s mean risk was 0.0317;
adaptive planning improved the risk-equivalent objective in 100% of scenarios.
The adaptive plan buys budget and cost stability by giving up a small amount of nominal risk reduction. That is the decision-relevant trade, not a claim that adaptation is free.
Scope
The experiment re-solves the exact MILP for the declared linear risk state. It does not establish global optimality for a nonlinear vegetation model, a full stochastic dynamic program, or a 10,000- segment network. Twenty-nine to thirty scenarios are a demonstration sample, not a calibrated probability model.