Fall-window capacity remedy

Observed-calendar awareness defers whole actions when the 75-day fall calendar cannot fit them. This remedy extends the work window to 90 and 105 days while holding the crew and machine mix fixed. It is an operational what-if, not a field schedule or a costed seasonal plan.

Results

20 episodes, seed 7.

Window days

Completed scope P50

Retained scope P50

Mean risk

Cost P50

Unscheduled h

Calendar deferrals

75

87.6%

87.6%

0.0502

264,047

0.0

39.9

90

95.9%

95.9%

0.0365

285,490

0.0

15.0

105

98.1%

98.1%

0.0333

294,012

0.0

4.6

The longer window recovers scope and lowers mean risk. Action cost rises because more work is retained; added seasonal overhead, supervision, and weather exposure are not modelled.

590-segment scale test

A replicated 590-segment instance scales the workforce to 30 crews and 30 machines. The fixed plan is exact; annual re-solves use Fresh Solutions.

Window days

Completed scope P50

Retained scope P50

Mean risk

Cost P50

Calendar deferrals

75

84.5%

84.5%

0.0667

2,536,614

484.3

90

95.9%

95.9%

0.0368

2,844,469

182.0

105

98.1%

98.1%

0.0328

2,931,649

58.8

Runtime: fixed exact 47.4 s; window sweep 244.9 s for 20 episodes. The remedy recovers almost all calendar-aware scope at scale. Action cost rises because more work is retained; added seasonal overhead, supervision, and weather exposure are not modelled.

Limits

  • Window extension is not a field calendar.

  • Crew and machine mix is held fixed.

  • No added seasonal overhead or supervision cost.

  • Whole-action deferral; no partial treatment credit.

  • No safety, access, asset-owner priority, or field-calibration claim.