Out-of-sample recovery
The fixed-factor recovery test reused the original annual factors for 2028-2031. This test keeps the first-year risk-ranked deferral fixed and resamples future cost, productivity, and capacity factors independently for each future path.
Future years are re-solved with the rolling persistence forecast and a two-year lookahead. This is a stochastic recovery test, not a stochastic dynamic program.
Method
20 rolling episodes.
First-year risk-ranked deferral: 20% target, 21.3% actual mean deferral.
Five independent future-factor paths per episode, 100 paths total.
2028-2031 re-solved for each path.
Future factors sampled from the same lognormal assumptions as the rolling policy.
Results
Metric |
P10 |
P50 |
P90 |
Mean |
|---|---|---|---|---|
Final risk gap |
-0.0078 |
-0.0010 |
0.0072 |
-0.0008 |
Recovery |
0.0340 |
0.0421 |
0.0491 |
0.0421 |
Final gap within 0.005 |
— |
87.0% of paths |
— |
— |
A negative final gap means the reoptimized path ends below the full policy’s final risk. The median gap is slightly negative; 87% of paths are within 0.005 of the full policy.
Cost bands:
reoptimized: 284,835-286,788 CAD, mean 285,868;
no reoptimization: 227,290-272,072 CAD, mean 251,312;
full policy: 273,213-326,472 CAD, mean 299,052.
The reoptimized path spends more than no reoptimization to recover risk, but less than the full policy on average.
Limits
First-year deferral is fixed.
Future factors are independent draws; no serial correlation or calibrated forecast process.
Future years use a persistence forecast and two-year lookahead, not a stochastic dynamic program.
First-year risk ranking only.
No recurrence, weather, outage, safety, or asset-owner priority model.