Risk-ranked scope deferral

The proportional scope remedy defers hours mechanically. This comparison instead defers whole first-year actions ranked by lowest first-year risk reduction per hour, until about 20% of action hours are deferred.

This is first-year risk ranking, not a multi-year risk model. The actual deferred fraction can overshoot because whole actions are selected.

Network result

  • 20 rolling episodes, 50 calendars per episode.

  • Target 20% of first-year action hours.

  • Mean actual deferred fraction: 21.3%.

  • Mean first-year risk loss: 0.0413.

  • Mean residual risk: 0.1546 (from a lower full-plan risk).

  • Median total cost: 47,226 CAD, budget-feasible in 100% of scenarios.

Case

Scenario completion

Mean risk loss

Residual risk

Budget feasible

Risk-ranked 20% + 75-day

47.1%

0.0413

0.1546

100%

Risk-ranked 20% + 105-day

87.4%

0.0413

0.1546

100%

For context, a proportional 20% reduction has an estimated mean first-year risk loss of about 0.0448 under the same action-benefit accounting. The risk-ranked choice loses less first-year risk reduction, but its whole-action selection also has lower scheduling completion than the proportional 20% + 105-day case.

Interpretation

The risk-ranked 105-day case completes less of the assumed calendar than the proportional case, but it protects more first-year risk reduction per deferred hour. Neither result is a multi-year risk recommendation. A real deferral decision would need year-specific risk accounting, recurring treatment effects, and asset-owner priorities.

Limits

  • Ranking uses first-year risk reduction per action hour only.

  • Whole segment actions are deferred; actual deferred fraction can overshoot the target.

  • No multi-year risk, treatment recurrence, outage, or safety model.

  • Weather and outage assumptions are prototype values.

  • The MILP is exact only for the declared linear risk state at 59 segments.